  • Question

  • If I have a task say 4 days, have a resource at $100 per day, status date is after the 2nd day, baselined and % complete is 25% my ACWP is $100.  However if the resource had additional costs so I am charged $150 and not $100 how can this be included in the ACWP figure?

    Cheers

    James


    Andrew Binnz

    Wednesday, May 11, 2016 10:54 AM

Answers

  • Hi,

    You could add a 50$ fixed cost so it'll be added to the acwp. By default fixed cost are accrued prorated, but you could change it to start, so the 50$ will be considered as spent at the start of the task, so immediately included in the acwp.

    Before:

    After:


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCC |

    • Marked as answer by JamesP435 Wednesday, May 11, 2016 1:23 PM
    Wednesday, May 11, 2016 11:06 AM
    Moderator

All replies

  • Hi,

    You could add a 50$ fixed cost so it'll be added to the acwp. By default fixed cost are accrued prorated, but you could change it to start, so the 50$ will be considered as spent at the start of the task, so immediately included in the acwp.

    Before:

    After:


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCC |

    • Marked as answer by JamesP435 Wednesday, May 11, 2016 1:23 PM
    Wednesday, May 11, 2016 11:06 AM
    Moderator
  • Thanks Guillaume 

    I thought I had done this but clearly not.

    Cheers

    James 


    Andrew Binnz

    Wednesday, May 11, 2016 1:23 PM