Summary Tasks are "Fixed Work" RRS feed

  • Question

  • We are using desktop Project 2010 Professional.  To build a new project a csv file is generated from Deltek's Costpoint database and then imported into Project.  We use fixed work tasks but instead of the tasks rolling into fixed duration summary tasks, the summary tasks are coming into Project as fixed work.  From what I've seen researching this online ... summary tasks are always fixed duration.  Will this effect any scheduling?
    Sunday, December 2, 2012 2:53 PM

All replies

  • Hi,

    that you can't change task type for summary tasks should not have any effect. At least as long as you follow highly recommended advice to NOT assign any resources to summary tasks. Task type has only impact on assignment, which you really should not have there.

    Regards
    Barbara

    • Proposed as answer by Naweed Jaulim Tuesday, December 4, 2012 4:13 PM
    Sunday, December 2, 2012 2:57 PM