    When we are using the Single Entry Mode in PWA 2010, is the PM still able to enter progress on tasks in Project Pro?

    Thanks

    Tuesday, February 22, 2011 3:29 PM

Answers

  • Hi,

    yes, they will. As long as you are not activating "Only allow task updates via Tasks and Timesheets" in Server Settings - Task Settings and Display as mentioned in an earlier post.

    Take care that a PM doesn't enter hours for a period already submitted.

    Regards
    Barbara

    • Marked as answer by WLID1966 Tuesday, February 22, 2011 5:43 PM
    Tuesday, February 22, 2011 5:31 PM
    Moderator

All replies

  • Hi,

    yes, they will. As long as you are not activating "Only allow task updates via Tasks and Timesheets" in Server Settings - Task Settings and Display as mentioned in an earlier post.

    Take care that a PM doesn't enter hours for a period already submitted.

    Regards
    Barbara

    • Marked as answer by WLID1966 Tuesday, February 22, 2011 5:43 PM
    Tuesday, February 22, 2011 5:31 PM
    Moderator
  • Hi,

    just an addition: if Administrator closes a time period, users will not be able to enter any hours in Tasks or Timesheet with SEM enabled. However, PM will be able to do so in Project client. I suggest to make this a training issue, if you want PMs to enter Actual Work into project plans. Not sure, if this will still be necessary, since there is now the feature delegation.