Tasks created in PWA are not visble in project schedule RRS feed

  • Question

  • In Project Server 2013 PWA in Tasks.aspx page
    in the Ribbon there is an option "Add Row"->"Add A new Task"

    After you add the task like this, you can also reassign the task to another user, and it will appear in his Tasks page. But this tasks do not become visible in project Schedule.

    Only when you open the project with "Project Professional" these tasks appear there, so you can publish it back and they will appear in Schedule. Why don't they appear immediately?

    Friday, November 23, 2012 6:01 PM

Answers

  • Hi MOSSImprisoned,

    You can republish the plan by clicking on "Publish" button in the Task Ribbon, which you can see once you will visit the schedule PDP in the PWA.

    Regards,

    Avinash kumar


    Avinash kumar | e2eProjects Pvt. Ltd | Blog:http://om-avinash.blogspot.com


    Saturday, November 24, 2012 8:29 AM
  • One remark: In "PS 2013" Publish appears in "Task" Ribbon in Schedule PDP
    • Marked as answer by Ross Ivantsiv Tuesday, November 27, 2012 4:43 PM
    Tuesday, November 27, 2012 4:43 PM

All replies

  • Because these new task requests need to ba approved by the PM before they are added to the plan. The plan must also be republished to make these tasks publicly visible.

    The New Task/Delete Task etc. are simply Team Member requests for a PM action. The PM is still the gatekeeper.

    Hope this helps.

    Treb Gatte | @tgatte | http://AboutMSProject.com

    Friday, November 23, 2012 6:04 PM
    Moderator
  • Treb,

    With approval everything is clear, i just forgot to mention this step:

    1. User adds a task with "Add Row"->"Add New Task"

    2. PM approves it

    and task is still not visible in project Schedule.

    You say "plan must be republished" - here is the question - how to republish it without Project Professional involved. Is it possible?

    Thanks for help anyway.

    Friday, November 23, 2012 6:21 PM
  • Hi MOSSImprisoned,

    You can republish the plan by clicking on "Publish" button in the Task Ribbon, which you can see once you will visit the schedule PDP in the PWA.

    Regards,

    Avinash kumar


    Avinash kumar | e2eProjects Pvt. Ltd | Blog:http://om-avinash.blogspot.com


    Saturday, November 24, 2012 8:29 AM
  • One remark: In "PS 2013" Publish appears in "Task" Ribbon in Schedule PDP
    • Marked as answer by Ross Ivantsiv Tuesday, November 27, 2012 4:43 PM
    Tuesday, November 27, 2012 4:43 PM
  • In PS10 Publish button is there in Task tab only.

    Avinash kumar | e2eProjects Pvt. Ltd | Blog:http://om-avinash.blogspot.com

    Wednesday, November 28, 2012 9:10 AM