none
The assignments in baseline 7 have disappeared RRS feed

  • Question

  • HI All,

    I'm using Project Server 2010.

    I've found several times this problem, but this one is the first time that I have the evidence. I have 2 environments, the PRODuction one and the TEST one. Sometime on the middle of January I restored the databases in the test environment, and now I can see the difference between them.

    there is a project manager that saved the baseline 7 on 28/12/2012, I have this baseline on this date in both environments, but the assignments in the Production Environment are not there anymore.

    Here you have the a copy of the screen when I select this infomration in the Production environment:

    And here you have the same information coming from the Test environment:

    It is the same baseline, when you open the project in Project Professional it tells you that the baseline was saved on 28/12/2012 in both cases.

    Do you know how is it possible? I'm really thinking that I will have to open a case incident in Microsoft, but I prefer to publish it here before (just in case you know what has happened here).

    Thank you for your help and regards,

    José Espases

    Monday, February 18, 2013 5:03 PM