Resource Engagement vs. Task Assignments (Work) - Project specific RRS feed

  • Question

  • We are running into an issue when trying to compare the Committed Engagement to the Assigned Work in a specific project only.

    Our organization does initial top-down planning, reserving resources via an engagement, then fills out the project plan based on the work that needs to be completed.  I am trying to find a view that will show if the work that has been assigned is within the bounds of the engagement that was originally requested.

    The Resource Plan view is close, but this is showing all the work that has been assigned to the resource across the enterprise, which is more information than what is needed.  What we want to know is, if we reserved 160 hours worth of work via an engagement for a project, have we under/over-allocated the assignments in that project schedule?

    Thanks in advance!