How can I add Publish column in Project schedule in Project server 2013? RRS feed

  • Question

  • How can I add Publish column in Project schedule in Project server 2013? Please advise....
    Tuesday, November 17, 2015 2:34 PM

Answers

  • Umesh --

    Open the enterprise project and then apply any task view, such as the Gantt Chart view.  Right-click on the Duration column header and select the Insert Column item on the shortcut menu.  In the list of available fields, select the Publish column.  Hope this helps.


    Dale A. Howard [MVP]

    Tuesday, November 17, 2015 3:12 PM
    Moderator

All replies

  • Umesh --

    Open the enterprise project and then apply any task view, such as the Gantt Chart view.  Right-click on the Duration column header and select the Insert Column item on the shortcut menu.  In the list of available fields, select the Publish column.  Hope this helps.


    Dale A. Howard [MVP]

    Tuesday, November 17, 2015 3:12 PM
    Moderator
  • Thank you Dale for your help. It works for me.

    Cheers!!!

     