  • Question

  • I created an Enterprise Custom Field as a Task Entity.  When I try to add the ECF to the Task Non Timephashed cube, the field does not display when I try to use it as Cube measure and select the Task cube.  It does show up when I select Assignment cube. Why???  TIA!

    Thursday, April 18, 2013 6:48 PM

All replies

  • How is the field defined.  Certain types do not build in the cube and if you use multi-select, the cube will not use that type of custom field.s

    Cheers!


    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

    Friday, April 19, 2013 3:27 AM
    Moderator
  • It is just a regular custom field that is numeric and clearly defined as a Task field.  The problem is that it is being built in a cube - Assignment instead of Task!

    Thanks for the reply!

    Friday, April 19, 2013 11:34 AM
  • How can that be normal?  All of my other custom fields I need for the scorecard are in the Task Cube.  Time to find another solution...