How do we spread 44hrs such as the distribution is 8h/day the first three days and 10 h/day the last two days? RRS feed

  • Question

  • Hi,

    How do we spread 44hrs such as the distribution is 8h/day the first three days and 10 h/day the last two days?

    Please, find below the scenario:
    * Create one resource (max units = 100%)
    * Create a task for a period of five working days, Effort driven and Fixed Duration
    * Assign the resource to the task
    => Result (1): The Work of 40hrs was distributed at a rate 8h/day.

    * Increase the Work with 4hrs

    QUESTION: How do we spread 44hrs such as the distribution is 8h/day the first three days and 10 h/day the last two days?

    THANK YOU FOR YOUR SUPPORT

    Wednesday, August 21, 2013 1:29 PM

Answers

  • H. Fayol,

    Go to the Resource Usage view and manually adjust the hours for the last two days. You do realize that the resource will be overallocated on those two days, right?

    John

    • Marked as answer by H. Fayol Thursday, August 22, 2013 9:29 AM
    Wednesday, August 21, 2013 2:18 PM

All replies

  • H. Fayol,

    Go to the Resource Usage view and manually adjust the hours for the last two days. You do realize that the resource will be overallocated on those two days, right?

    John

    • Marked as answer by H. Fayol Thursday, August 22, 2013 9:29 AM
    Wednesday, August 21, 2013 2:18 PM
  • Hi John,

    Thank you for taking the time to answer.

    "You do realize that the resource will be overallocated on those two days, right?"

    Yes. I have tried to reprocude the exemple used in the following article: ttp://blogs.msdn.com/b/project/archive/2010/04/29/assignment-units-in-project-2010.aspx

    Regards, H.F.

    Thursday, August 22, 2013 9:28 AM
  • H.Fayol,

    You're welcome and thanks for the feedback. It looks like you found a good reference to help understand how it all works.

    John

    Thursday, August 22, 2013 2:40 PM