Hi,
I am trying to create a resourcing spreadsheet for a project (with the future idea to roll multiple projects up into a programme resource view). At the moment we do not have specific people assigned to specific tasks (e.g bob does task x), but rather a pool
of general resource (e.g 1x Project Manager).
Currently I have two tasks, that will both happen in the month of October, using the same person. However the task is just 1 day within that month. I have used the fixed duration and the costs are coming out correctly, however, it will not allow me to make
task 2 a predecessor of task 1 without moving out the dates, even though it is only 1 day within that time period that each task needs.
Is there a way around this?