    I have a project plan in which the actuals are not showing up! The timesheets as well as the status updates have been aproved and published but still the Actuals are not showing up ! I checked in the database and the values are present there but somehow it is not making its way into the project plan.

    What to do guys ? Please help !

    Thanks

    Wednesday, August 7, 2013 6:12 AM

All replies

  • Hi

    1] Clear the local project cache and open the project again and check.

    2] Open the project from Publish database and check if the actual work is showing.

    3] There is one such actual work getting deleted is resolved in October 2012 CU http://support.microsoft.com/kb/2687612

    The below information is from the above article

    "Assume that you have a task that has more than one resource assigned and at least one of the assigned resources has no Actual Work associated with it. Then you use the Update Projectoption to reschedule work for a time before the task's start date. In this scenario, all existing Actual Work for the assignments on the task is deleted."