Working hours automatic replanning RRS feed

  • Question

  • Hello,

    I have big problem with MS Project 2016 replanning workers working hours. Since I can't upload image I will create pattern how work was planned:

    1. 7 8 7 8 8 - - 7 8 7 8 8 - - 7 8 7 8 8 (Fixed Units)
    2. 8 7 8 7 8 - - 8 7 8 7 8 - - 8 7 8 7 8 (Fixed Units)
    3. 7 8 7 8 8 - - 7 8 7 8 8 - - 7 8 7 8 8 (Fixed Work)
    4. 7 8 7 8 8 - - 7 8 7 8 8 - - 7 8 7 8 8  (Fixed Duration)

    So I was planning work for three weeks. 1st, 3rd and 4th Tasks had seven working hours on Mondays and Wednesdays (entered manually). Task 2nd had seven working hours for Tuesday and Thursday (entered manually). After my team members sent exactly the same amount of working hours as I had planned project decided to move next weeks seven hours working days one day ahead and totally change third weeks plan. Also i have no idea why 4th (Fixed Duration) task increased the number of hours:

    1. 7 8 7 8 8 - - 8 7 8 7 8 - - 8 8 8 8 6
    2. 8 7 8 7 8 - - 8 8 7 8 7 - - 8 8 8 8 6 
    3. 7 8 7 8 8 - - 8 7 8 7 8 - - 8 8 8 8 6
    4. 7 8 7 8 8 - - 13,22 11,57 13,22 11,57 13,22 - - 13,22

    Any ideas why this is happening? Do I have faulty program or something?

    Thank you in advance.
    Tomas.