none
Schedule Performance Indicator (SPI & CPI) consolidate values are not displaying in master project RRS feed

  • Question

  • Hi,

    I have created a view in Project center for Earned value method by creating custom filed with formulas, i can able to see all the values. But we are not able to see the consolidate value of CPI & SPI on a master project.

    We can see all the remaining values but these 2 values are not displaying, below is the screen shot. Please let me know is it a default behavior.

    Please suggest on this.

    


    Geeth If you feel that the answer which i gave you is Helpful please select it as Answer/helpful.

    Thursday, January 19, 2017 8:57 AM