How do I set a 4 day work week 10 hrs a day? RRS feed

Answers

  • Hi,

    you haven't mentioned the version?

    2010:
    Tab Project - Change Working Time. Tab Work Weeks - click on button Details. Select your working days (e.g. Mon-Thu) by using Shift or CRTL key. Select "Set day(s) to these specific working times".Enter your working times in grid. Select your additional non-working day and select "Set days to nonworking time.Close all dialogs.
    File - Options - Schedule. Make sure that your preferred option is selected in "Calendar options for this project" (I assume your actual project?) Change Default start time, Default end time hours per day and days per moth accordingly.

    2007:
    Tools - Change working Time. Tab Work Weeks - click on button Details. Select your working days (e.g. Mon-Thu) by using Shift or CRTL key. Select "Set day(s) to these specific working times".Enter your working times in grid. Select your additional non-working day and select "Set days to nonworking time.Close all dialogs.
    Tools - Options - tab Calendar. Change Default start time, Default end time hours per day and days per moth accordingly. Hit "Set as Default" only, if you want to have these setting applied for all projects.

    Does this help?