none
Auto update field based on change in another RRS feed

  • Question

  • Hello,

    I have created a custom cost field which I would like automatically copy to the normal cost field every time I change it.

    I've found articles relating to event handlers but none of the samples seem to work on project 2016

    Anyone have some advise?

    Thanks

    Wednesday, October 12, 2016 9:33 AM

All replies

  • Hello,

    Are you trying to do this in Project Pro or Server Side?

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS | MVP | Downloads

    Thursday, October 13, 2016 8:15 AM
    Moderator
  • Project Pro

    I have found the Sub App_ProjectBeforeTaskChange event handler that works ok, but everything I do in this sub occurs before the change in the selected field is applied.

    I then found the Proj_Change(ByVal pj As Project) event which is what I want, but it doesn't bring in any of the task objects......

    Thursday, October 13, 2016 9:23 AM