none
MSP 2010 Dynamic Linking Milestone issue RRS feed

  • Question

  • I am trying to dynamically link a milestone from a subproject into the master project area.  I have done about 30 links so far but now MSP 2010 is copyingthe milestone with a duration that totals the whole activity (ie 131 days).

    I can't change it back to zero duration as it breaks the link.

    I have tried to delete it and re-create the link but it doesnt fix it.

    Has anyone seen this error before and how do I fix it.

    I have 9 projects to link milestones from so have only just started.

    Wednesday, June 6, 2012 6:52 AM

Answers

  • Hi,

    I'm sorry but I couldn't understand the statement - MSP 2010 is copyingthe milestone with a duration that totals the whole activity (ie 131 days).

    Please elaborate on the steps you are performing.


    Sapna S

    Wednesday, June 6, 2012 7:44 AM
    Moderator