Not able to see timesheet line in approval center in Project Server 2010. RRS feed

  • Question

  • Hi,

    In Project Server 2010, when resources are trying to send the status of “selected tasks” or “all tasks” from submit section of ribbon, their timesheet manager is not able to receive the timesheet line for approval. However if resources use the option “send timesheet”, manager gets the whole timesheet for approval. We want resources to send the status of selected tasks on regular basis. How we can do that?


    Gaurav Goyal
    Thursday, February 10, 2011 1:13 PM

Answers

  • Hi,

    ask project manager of your projects to have a look at Approval Center: I think they will see updated tasks there. Do they?

    Timesheets and Task updates are two separate entities by default.
    Timesheets go to the timesheet manager (normally the resources direct Managers like a line manager), task updates submitted by sending the status of “selected tasks” or “all tasks” will be sent to project managers for approval.

    Regards
    Barbara

    Thursday, February 10, 2011 1:52 PM
    Moderator