  • Hi All

    Bit of an odd one this - I have a fairly straightforward project comprising numerous tasks and milestones. These are linked using task dependancies in the usual way, on screen all looks tickerty boo.

    However, I've just noticed when printing a gantt chart (to pdf) that the dependancies bewteen  milestones are shown going to the baseline milestone dates rather than against planned milestone dates. Any reason for this ???

    Thanks, Swansea Jack

    Monday, November 18, 2013 10:48 AM

All replies

  • Hi Jack,

    I'm guessing the link lines appear correctly in the Gantt chart?  What service pack is installed?  If you are using Project 2010, you should have SP-2 installed.

    Does this occur in all files or just one?

    Monday, November 18, 2013 11:26 AM
    Moderator
  • Hi Julie

    Thanks for your reply. I'm using MSP 2013 - and it should have all the latest SP's included (done automatically).

    Swansea Jack

    Monday, November 18, 2013 2:17 PM
  • Hi Jack,

    Project 2013 has had several cumulative updates (CU) released.  They are not installed automatically.  The June 2013 CU addressed some printing issues.  I have it installed and am unable to reproduce what you report.

    You may try installing the CU to see if it helps.

    http://support.microsoft.com/kb/2817338/en-us

    Julie

    Monday, November 18, 2013 5:19 PM
    Moderator