  • I have a task that was part of a sub-task.  I tried to out-dent it and it turned it into a summary task.  I didn't want it to be a summary task.   I tried sending it back to the original position I had it in but it will not change it back.   It kept it as a summary task.  I can't delete it because of course it will delete all of the sub-task below it.  Deleting the sub-task is not an option since I already have approx. 400+ lines of other summary task and sub-task in the plan.   I have researched but can't find why I can't change this task back. Desperately need help