Is any way "process status (assignment)" field available for reporting or to use it in task level formula in project online RRS feed

  • Question

  • Is any way "process status (assignment)" field in task page available for reporting in project online.

    Can i use it in task level formula to show indicator based on it's status. Though i can't see it.


    sandeep



    Thursday, October 26, 2017 6:00 AM

All replies

  • Many fields in the published schema are not available in reporting and this is one of them.  