PWA 2016 capacity planning displaying wrong results RRS feed

  • Question

  • After upgrading from Project Server 2013 to 2016 version, Capacity planning view (/PWA/_layouts/15/PWA/RM/CapacityPlanning.aspx) is not displaying actual availability and capacity times correctly.

    When I choose "Work by Resource", only for top user (alphabetically sorted) I see real Availability, Capacity and Project Assignments per project. For all other users Capacity value is equal to Availability and Project Assignments are not displayed. If I am selecting resources one by one then clicking "Capacity Planning", I can see correct  Availability, Capacity and Project Assignments per project.

    Had anyone faced such issue?


    • Edited by ArturAIM Wednesday, February 7, 2018 12:57 PM
    Wednesday, February 7, 2018 12:41 PM

Answers

  • Here is the answer I got from Microsoft support yesterday:

    "I discussed the case with the Escalation team and I got the information that this is a known issue with SharePoint ON PREMISE and online both and this issue will be fixed in April 2018 PU (16.0.4674.1000). 

    So yes Microsoft Project Development team is working on it.
    Approximate date is around 15 April as it will fix in April 2018 PU."

    • Marked as answer by ArturAIM Thursday, March 8, 2018 6:50 PM
    Thursday, March 8, 2018 6:49 PM

All replies

  • I have this same problem after an update from 2013 to 2016. Any solution?
    Thursday, March 8, 2018 6:24 PM
  • Here is the answer I got from Microsoft support yesterday:

    "I discussed the case with the Escalation team and I got the information that this is a known issue with SharePoint ON PREMISE and online both and this issue will be fixed in April 2018 PU (16.0.4674.1000). 

    So yes Microsoft Project Development team is working on it.
    Approximate date is around 15 April as it will fix in April 2018 PU."

    • Marked as answer by ArturAIM Thursday, March 8, 2018 6:50 PM
    Thursday, March 8, 2018 6:49 PM