Approval Center RRS feed

  • Question

  • whenever manager assign a task to the resources and resource filling their task/timesheet and send to the manager but task/timesheet are not coming in manager approvals. task/timesheet are going in admin approval center why ? how I can change
    • Edited by somu1 Friday, May 2, 2014 12:24 PM
    Friday, May 2, 2014 12:22 PM

All replies

  • Hi,

    We would need further information in order to help you out. Project Server version? Single entry mode activated?

    Have you checked-out the timesheet status to see if there are any errors while submitting it?

    Then you have to differenciate the status manager that will approve the task updates on his project and the timesheet manager that will approve the entire timesheet. If you set in the timesheet settings that lines must be approved prior to the timesheet, then the timesheet manager will receive the approval request only after the status manager would have approved the task updates.

    See more details in this similar post:

    http://social.technet.microsoft.com/Forums/ie/en-US/ee9bce98-fc7a-458a-b048-a5903e2d590f/timesheet-and-project-server-issue?forum=projserv2010setup


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    Friday, May 2, 2014 12:27 PM
    Moderator
  • Hi,

    1 .We are using Project server 2013. and single entry mode activated.

    2. there is no any error occurs while submitting timesheet.

    3.and I have one question what is status manager ?

    4.I have using timesheet manager for approval the timesheet but there is no idea about status manager.

    thanks.

    Monday, May 5, 2014 9:12 AM
  • Hi,

    Thus your issue is about the status manager approval that is prior to the timesheet manager approval. Depending on how the timesheet approval chain is configured, the approval will not go to the timesheet manager before the status manager has approved the task updtaes.

    Please read this post on status manager:

    http://social.technet.microsoft.com/Forums/ie/en-US/ee9bce98-fc7a-458a-b048-a5903e2d590f/timesheet-and-project-server-issue?forum=projserv2010setup

    Another procedure here:

    http://epmablog.com/changing-the-project-manager-in-microsoft-project-server/



    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    Monday, May 5, 2014 11:07 AM
    Moderator
  • Please provide the following

    Who is project owner of Project?

    Who is status manager on Task?  Please sure to look this one up.

    Who is the timesheet manager of the resource assigned ?

    Who is doing the approvals?

    Check all the filters on the Approval page and verify that they are not on.

    Cheers


    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries


    Sunday, May 11, 2014 11:46 AM