Enterprise Custom Fields on Timeline RRS feed

  • Question

  • Is it possible to add an enterprise custom field value (date format) to the timeline view?

    The scenario is this:

    Milestones have two dates associated with them. The first is the red date which is the start/finish date of the milestone task. The second is the green date which is a date calculated based on the project schedule and may perhaps be the red date + up to 6 months.

    An enterprise custom field (date format) is used to record the green date per milestone.

    When a milestone is added to the timeline view, the date is defaulted to the start/finish date. Can we change this to display the date shown in the enterprise custom field? Or ideally, can we display both dates on the timeline?

    Tuesday, May 21, 2013 10:28 AM

Answers

  • Not via configuration.  Custom code may be possible.

    Reid McTaggart – DeltaBahn Vice President
    Blog | Twitter | LinkedIn Please click Mark As Answer; if a post solves your problem or Vote As Helpful if a post has been useful to you. This can help other community members reading the thread.

    • Marked as answer by Laura_ink Tuesday, May 21, 2013 4:41 PM
    Tuesday, May 21, 2013 2:55 PM