Resource leveling hangs MS Project RRS feed

  • Question

  • First, this is the product that I'm working with: Microsoft Project 2013 (15.0.4569.1504) MSO (15.0.4569.1506) 32-bit

    I created a project and assigned resources. When I go to level the resources, project hangs and doesn't return.  I cannot do any leveling - even for tiny projects. What do I need to do? Without leveling, project is useless.

    Thursday, March 16, 2017 7:47 PM

All replies

  • This often happens when there is a problem with one of two resources and you need to identify which resource(s) are causing it. Click on the ESC key and it will stop the project from hanging.

    Instead of using 'level all', click on one resource at a time (i.e level resource instead of level all).

    Once you identify which resource is causing the levelling to hang, you need to fix the issue with that, specific resource. You'll then be able to do level all.

    Sunday, May 28, 2017 12:29 PM