Is it possible to edit each resouce's actual work using PWA or CSOM in Project Server 2013? RRS feed

  • Question

  • Hi, in our project, each task can be assigned to multiple people. So we need every person to report his/her own actual work hours. Is this possible?

    I noticed in PWA, I can modify the whole task's actual work, but not each resource's. In Project Professional, it is possible to do that. However, the modifications are not reflected in Project Server. Even if I save the project and publish it, when I come back to PWA, I still see the automatically generated actual hour for each resource, and it is read only. The value seems always automatically calculated using the formula: (task's actual working hours)/(number of resources working on this task).

    In the end, we have to achieve the goal programmatically using CSOM (not PSI). But first I'd like to know if this scenario is possible. Thanks for any suggestions.


    Sining Oh Blue Star

    Monday, August 5, 2013 12:58 PM