Actual cost difference in Power BI report RRS feed

  • Question

  • I have a very strange thing that came up. I set my project plan NOT to calculate costs in settings as I manually enter it. So when a resources did not charge me for work planned I do not enter cost in the actual field. However when I pull the report in Power BI my costs were different. I then went into Project and made all the actual cost lines that I was not charged for 0 which solved my problem. However I do not think this should have happened, any idea on this?
    Friday, April 6, 2018 12:17 PM