Rsource Availability Report in Project Server 2013 RRS feed

  • Question

  • Hello, I am using Microsoft Project 2013. 

    I like how simple it is to get a report on Resource Availability via the Resource Center in PWA.  What I don't like though is that hours are reported to 3 decimal places.  Is there way to limit the decimal places in the results?  Thx.

    Wednesday, November 20, 2013 7:56 PM

Answers

  • As far as I know, there is no way to do it out of the box. An easier alternative is to develop a similar report with Excel Services or SSRS, and adjust there.

    Prasanna Adavi,PMP,MCTS,MCITP,MCT http://thinkepm.blogspot.com

    Thursday, November 21, 2013 2:27 AM