none
Change Working Time was Disable.. RRS feed

  • Question

  • Hi..

    Can anybody help me to enable features in Change Working Time form.

    I can't able to access (Create New Calendar, Add Calendar to enterprise) and in Exception Field (details).

    Thanks..

    Tuesday, April 4, 2017 5:40 AM

Answers

  • Hi,

    is it possible that you work with Project Server or Project Online? If this is the case, your administrator has not allowed to use locale calendars (Allow projects to use local base calendars ) in Server Settings - Additional Server Settings. There may be a reason for that due to process decsision or ist was just skipped. Please asl your admins for additional information.

    Regards
    Barbara


    Tuesday, April 4, 2017 8:11 PM
    Moderator