Is there any possibility to display work values in Project Center in PWA (remaining work, actual work, work, baseline work...) in days instead of hours? RRS feed

  • Question

  • Is there any possibility to display work values in Project Center in PWA (remaining work, actual work, work, baseline work...) in days instead of hours?

    Wednesday, August 1, 2012 11:35 AM

Answers

  • Ankit --
     
    No, this is not possible, at least not using any of the default features in Project Server.  An alternate approach would be to create a set of custom enterprise Duration fields containing formulas and named similar to their corresponding Work fields.  For example, create a custom enterprise Duration field named WK and then use the following formula:
     
    [Work]
     
    By using a custom enterprise Duration field, the system will automatically convert the Work value from hours to days.  You would need to create additional custom enterprise Duration fields to correspond with Actual Work, Baseline Work, and any other work-related fields in which you are interested.  Then you would need to include those custom fields in Project Center views and/or Project Details views as needed.  Hope this helps.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"