Different costs for the same resource and different tasks(construction project) RRS feed

  • Question

  • Hello Experts

    I am fairly new to MS project. I am asked to build a project timeline for a construction project. This phase only includes costs for the architect. He charges eg: General field time- 2 hours @ 150/hr and Site verification - 4 hours @75/hr. How do i deal with this scenario. How do I allocate different costs for the same resource and different tasks in the resource sheet. 

    Tuesday, January 19, 2016 5:45 PM

All replies

  • Swapna,

    You can use Cost Rate Tables to specify different costs for different assignments for the same resource.

    Please see this article for more details: http://epmainc.com/blog/using-alternate-cost-rates-resources


    Cheers,

    Prasanna Adavi, Project MVP