Change predecessor lag from edays to working days RRS feed

  • Question

  • How do you change the predecessor lag time back to working days instead of the newly defaulting edays in project 16?  This is extremely frustrating. Edays just do not fit for the way we schedule projects.  I have recently been put in charge of improving schedule performance for the 30+users in our office and we have found a number of mistakes made in schedules in our company using edays and  and we are considering having to downgrade all our software to an earlier version.  This is really frustrating.  Any help, is there a box I can check and get this basic and fundamental scheduling function back?