Creating a project in PWA and Calendar RRS feed

  • Question

  • Hi,

    How to attach a specific calendar to a new project you are creating in PWA (Project Online)

    Thanks

    Thursday, September 1, 2016 2:14 PM

Answers

  • Hi,

    You cannot change the calendar in PWA while creating the project. It will be by default the template's calendar. You need Project Pro to change the project's enterprise calendar.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    • Marked as answer by WLID1966 Thursday, September 1, 2016 2:43 PM
    Thursday, September 1, 2016 2:36 PM