Calculating Planned Work in Project Server RRS feed

  • Question

  • How is Planned time for Remaining Work calculated in Project Server 2010 when the Actual Start is later than expected.  Example:

    Original Start 03/14/2013, Original End 05/10/2013 with 2 hrs Work

    Actual Work of .5h was submitted on 04/10/2013 via Task Updates (not Timesheet).  Project Server re-calculated Planned Work for the remaining 1.5h to be .05h per day.  How is the .05h per day determined?

    Wednesday, April 10, 2013 6:19 PM