Proj Server 2010 Dashboard Designer Not Reporting Future Capacity RRS feed

  • Question

  • With information from Project Server 2010 (PWA) and using Dashboard Designer I’ve designed a time-phased report (by month) to show past effort (Measure - Actual Regular Work) against capacity (Measure – Capacity) which displays accurate information.  I’ve designed a similar report to show future planned work (Measure – Remaining Work) against capacity (Measure – Capacity).  Planned work reports accurately but for some reason this report does not show future capacity.  Resources in the pool have latest available dates.  Can someone please tell me what I need to do to report future capacity in Dashboard Designer?  Thanks in advance!

    Thursday, May 29, 2014 7:16 PM

All replies

  • Check the settings for Resource Capacity settings >> in additional server settings

    Also what is the report query looking at is it OLAP cube or Reporting DB ? if it is OLAP is the cube being built and what is the date range settings defined in OLAP ? How is the Query extracting the data ?

    it would be difficult to identify without having details


    Thanks | epmXperts | http://epmxperts.wordpress.com

    Thursday, May 29, 2014 7:33 PM
    Moderator
  • Resource Capacity Settings are set to:

    Months behind : 1

    Months ahead: 12

    The report uses Portfolio Analyzer Cube.  The OLAP cube builds every 24 hours.  Database date range is “Use the earliest project start date and the latest project finish date”. 

    Thank you for your help.

    Monday, June 9, 2014 6:53 PM