  • I have drawn up a construction work programme that runs over 15 months and now I would like to know how do I see a percentage complete forecast for the next 15 months, i.e. by month 3 we should be 23% complete, following month 29%, etc. etc.
    Tuesday, August 23, 2016 4:28 AM

All replies

  • Hi 10111ivan,

    You need to mark tasks as on-track...  This will update the status of the tasks.  The simplest way to do this would be to use the Update Project dialog box as per the screen shot.


    Ben Howard [MVP] | web | blog | book | P2O

    Tuesday, August 23, 2016 6:37 AM
    Moderator
  • If you need to see the predicted % complete by month, then:

    1.  Save you project and set the whole project to 100% complete.
    2. Then apply the Task Usage Task Usage view.
    3. Right-click the main yellow area and select Detail Styles..
    4. Add Cumulative % complete to the Show fields
    5. Click OK
    6. Adjust timescale to monthly to see a predicted monthly % complete

    Save the project for reference with a different name.

    More useful is saving a baseline if you haven't already. That way when you accurately update when tasks actually happen you get a more accurate view of performance.


    Rod Gill
    Author of the one and only Project VBA Book
    www.project-systems.co.nz


    Wednesday, August 24, 2016 11:40 PM