  • Question

  • Hi,

    I use MS Project 2010, and i wonder if it is possible to change the % completed to weight cost instead of duration? 

    An example:

    33%

    1 5d 100% $5000

    2 5d 0% $2500

    3 5d 0% $2500

    I want the %completed to turn out as 50%, as 50% of the cost is used.

    Thursday, October 8, 2015 7:13 PM

Answers

  • Monica,

    Well, "no" and "yes". No, you can't change the existing Percent Complete field to do what you want, but yes, you can create a custom field to do what you want. Use the following formula. Don't forget to set the calculation for group and summary rows to "use formula".

    Text1=[Actual Cost]/[Cost]*100 & "%"

    Hope this helps.

    John

    Thursday, October 8, 2015 8:16 PM

All replies

  • Monica,

    Well, "no" and "yes". No, you can't change the existing Percent Complete field to do what you want, but yes, you can create a custom field to do what you want. Use the following formula. Don't forget to set the calculation for group and summary rows to "use formula".

    Text1=[Actual Cost]/[Cost]*100 & "%"

    Hope this helps.

    John

    Thursday, October 8, 2015 8:16 PM
  • Hi 

    Thanks :)

    This is what i want, but the problem is that it don't show "%", it shows $.

    How to type the formula so it shows %

    :)

    Friday, October 9, 2015 7:21 AM
  • Monica,

    Apparently you didn't customize a text field as I indicated in my response. Doing it as I suggested will definitely give the results you want.

    Try again.

    John

    Friday, October 9, 2015 2:41 PM
  • Thanks John,

    I did what you said, and that worked :)

    M

    Friday, October 16, 2015 2:09 PM
  • Monica,

    You're welcome and thanks for the feedback.

    John