    Which calendar does Project use to schedule a resource in a project - The project calendar or the base calendar the resource is assigned to on the server side?


    Judy Washington

    Tuesday, May 28, 2013 6:34 PM

Answers

  • Judy,

    All tasks use the Project calendar by default. And all work is scheduled based on the resource's calendar if it is different from the project calendar. There could also be a custom calendar created for one or more tasks.

    So to answer your question directly, the resource calendar.

    John

    • Marked as answer by Judy IPD Tuesday, May 28, 2013 8:08 PM
    • Unmarked as answer by Judy IPD Tuesday, May 28, 2013 8:08 PM
    • Marked as answer by Judy IPD Tuesday, May 28, 2013 8:09 PM
    Tuesday, May 28, 2013 7:57 PM

All replies

  • Judy,

    All tasks use the Project calendar by default. And all work is scheduled based on the resource's calendar if it is different from the project calendar. There could also be a custom calendar created for one or more tasks.

    So to answer your question directly, the resource calendar.

    John

    • Marked as answer by Judy IPD Tuesday, May 28, 2013 8:08 PM
    • Unmarked as answer by Judy IPD Tuesday, May 28, 2013 8:08 PM
    • Marked as answer by Judy IPD Tuesday, May 28, 2013 8:09 PM
    Tuesday, May 28, 2013 7:57 PM
  • Thank you John. That is what I was looking for.


    Judy Washington

    Tuesday, May 28, 2013 8:09 PM
  • Judy,

    You're welcome and thanks for the feedback.

    John

    Tuesday, May 28, 2013 8:31 PM