Assignments Keeping Outline Structure grouping in Project Pro RRS feed

  • Question

  • Hi,

    I'm using Project Pro connected on Project Online. In the Resource Usage view, I activated the "Assignments Keeping Outline Structure" grouping. 

    For some resources,  the "Other projects and committments" is multiplied by 2.(For the ANALYSTE below).  For some other resources, the caculation is right. What could be the issue ?

    Thanks