none
% Work Complete not rolling up to the summary level tasks RRS feed

  • Question

  • I see that for few of the tasks in my project plan % work complete is not rolling up appropriately on to the Summary level tasks; no matter what % I update its not rolling up as expected.

    Thursday, March 27, 2014 6:35 AM

Answers

  • Please check that resources are assigned on all the tasks as the % Work Complete uses the formula Actual Work/Work X 100; so sometimes if on few tasks, under a Summary, resource are not assigned  - then you may see different figure in %work complete then expected. Please let us know if it resolves the issue.


    Sapna Shukla

    • Marked as answer by AdhyaB Thursday, March 27, 2014 8:17 AM
    Thursday, March 27, 2014 8:09 AM
    Moderator

All replies

  • Please check that resources are assigned on all the tasks as the % Work Complete uses the formula Actual Work/Work X 100; so sometimes if on few tasks, under a Summary, resource are not assigned  - then you may see different figure in %work complete then expected. Please let us know if it resolves the issue.


    Sapna Shukla

    • Marked as answer by AdhyaB Thursday, March 27, 2014 8:17 AM
    Thursday, March 27, 2014 8:09 AM
    Moderator
  • Yes this was the issue and it resolved thanks
    Thursday, March 27, 2014 8:17 AM