  • I have a project with some inactive tasks. The tasks and associated resources appear as inactive in the task usage view. When you print from the task usage view, some of the inactive tasks and the associated resources appear to be active, meaning they aren't grey and don't have the strike through. The tasks without the correct formatting in the print view are all milestones, but the resources seem to be random- there is no obvious reason (that I can see) why they wouldn't be formatted correctly.

    I am using Project Professional 2013 and Project Server 2013.

    Has anyone noticed this or got a solution?

    Thanks

    Tuesday, October 6, 2015 3:55 PM