mutilple calenders in PWA 2010 RRS feed

  • Question

  • Can add a calendar for international  holidays to enterprise.Would  it  be possible to set working on weekend when add the calendar for International holidays?

    Thursday, May 22, 2014 2:35 PM

All replies

  • Yes Possible to create an enterprise calendar with enterprise holidays and change weekends as working, check this article

    http://technet.microsoft.com/en-us/library/gg982970%28v=office.14%29.aspx


    Thanks | epmXperts | http://epmxperts.wordpress.com

    Thursday, May 22, 2014 2:45 PM
    Moderator
  • we are a Canadian company and wants to set up US holiday calendar can we have 2 calenders with different working times?
    Thursday, May 22, 2014 2:52 PM
  • Yes you can have multiple enterprise calendars and then associate each calendar to individual project or resource or tasks

    Thanks | epmXperts | http://epmxperts.wordpress.com

    Thursday, May 22, 2014 2:54 PM
    Moderator
  • How can I associate it by Resources?
    Thursday, May 22, 2014 2:55 PM
  • In PWA 2010, navigate to the Resource Center, select the resoiurce you want to associate the calendar to, edit resource and set the field Base Calendar to the one you wish.

    This can also be done via Project professional, if it needs to be done in Bulk.


    Prasanna Adavi,PMP,MCTS,MCITP,MCT http://thinkepm.blogspot.com

    Thursday, May 22, 2014 3:01 PM
    Moderator
  • Is there a way I can import US stats holidays in new calendar and not by manually typing it?
    Thursday, May 22, 2014 3:06 PM
  • Hi Project Help,

    There is an app in PS2013 for sync holidays, but I don't think such a tool exists for PS2010.

    In case I'm right, you'll have to enter them manually. Anyway note that you can enter recurring days-off. Meaning that you can specify that the canada day will occur on july 1st yearly or even every 3rd monday of may for another day off.

    See reference here: http://ntrajkovski.com/2013/11/07/recurring-week-exceptions-in-ms-project-2013/


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    Thursday, May 22, 2014 3:37 PM
    Moderator
  • thanks I will

    so if i add New calendar it will not effect existing resources and projects timings?

    Only when I assign resources to that new calendar?

    Thursday, May 22, 2014 4:20 PM
  • Exactly. Creating a new calendar will have no effect unless you assign it to a project or to resources and publish the impacted projects.

    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    Thursday, May 22, 2014 4:31 PM
    Moderator
  • By Adding do you mean just adding to the enterprise or changing it to the resource calendar

    if its just adding it won't have nay impact, but if you change the resource or project calendar to new one it may have impact on the work / duration ...


    Thanks | epmXperts | http://epmxperts.wordpress.com

    Thursday, May 22, 2014 4:34 PM