locked
Sharepoint 2007 GANNT chart view RRS feed

  • Question

  • Hi,

    I have GANNT chart which is a two week look ahead.  I use a filter on a due date to only display tasks due in the next two weeks.  However the GANNT chart goes out several months, so it looks like nothing is due three weeks and beyond.  

    How do I get the GANNT chart to only show a time range from now until two weeks,

    Thanks,

    Bryan

    Wednesday, June 12, 2013 12:10 AM

All replies

  • You can use a filter in the view creation screen for this.  Use the due date, set the filter to "less than" and put [Today]+14 in the filter box.  This should show anything due in the next two weeks only.

    Steven Andrews | SharePoint Professional | http://www.twitter.com/backpackerd00d | https://baron72.wordpress.com/

    Wednesday, June 12, 2013 9:15 AM
    Answerer
  • Hi Steven,

    This filter is successful in displaying the correct data, however my problem is in the GANNT chart itself.  I have data displayed out to [Today]+14, but the chart itself goes out several months.  This gives the false impression that on [Today]+15 there are no tasks due, even though that data is purposely not shown.  I need some way to make the chart itself stop at [Today]+14, so that other viewers of that chart do not get a false impression.

    Thanks,

    Bryan

    Wednesday, June 12, 2013 2:33 PM