Split Tasks Won't Be Moved to Certain days RRS feed

  • Question

  • Project 2016 suddenly won't allow me to move individual splits to certain days of the week e.g. I can make a split at the end of the first period, but then when I move the start date of the other side of the split to say, Wed, it will only allow me to move the date to the Mon or the Thu but not Tue or Wed, a two day gap!!
    Saturday, November 30, 2019 5:52 AM

All replies

  • MJCussen,

    On the surface it sounds like a calendar issue but we need a little more information in order to help you much further.

    What is your Project calendar?

    Is the Base Calendar of the resources assigned to the task the same as the Project calendar or do those resources have separate resource calendars?

    Does the task you are trying to split have a task calendar and if so, what is it?

    What is the start date of the task?

    What is the duration of the task?

    How many resources are assigned to the task?

    Does the task you are trying to split have any actuals?

    John


    Saturday, November 30, 2019 4:20 PM