  • Hi. I need a little assistance with MS Project 2010 please.

    2 columns in my Gantt chart are labelled "Scheduled Start" & "Scheduled Finish". They show the start & finish dates of each task. However, my tasks have short durations. Is there a way to format the columns to show start & finish times & not dates.

    Any suggestions would be much appreciated

    Thank you.

    Cionn

    Tuesday, February 12, 2013 8:45 AM

Answers

  • Hi Cionn,

    Try changing the date format.

    File menu >> Options >> General >> Date format.

    Thanks,

    Kiran K.

    • Proposed as answer by Kiran Khanvilkar Tuesday, February 12, 2013 9:06 AM
    • Marked as answer by Cionn Tuesday, February 12, 2013 9:09 AM
    Tuesday, February 12, 2013 8:55 AM

All replies

  • Hi Cionn,

    Try changing the date format.

    File menu >> Options >> General >> Date format.

    Thanks,

    Kiran K.

    • Proposed as answer by Kiran Khanvilkar Tuesday, February 12, 2013 9:06 AM
    • Marked as answer by Cionn Tuesday, February 12, 2013 9:09 AM
    Tuesday, February 12, 2013 8:55 AM
  • Thanks Kiran.

    So simple. I never would have thought of that.

    Thank you

    Cionn