Issue in WORK and ACTUAL WORK RRS feed

  • Question

  • Hi

     

        am using MS Project 2003 connected with Project server 2003. In My project i have 8-10 Summary

    task for all the summary task it shows correct WORK and ACTUAL WORK except one and all its independent(SS Relationship)

     

    Task Name        Work                Actual Work

    XXX             5000000 hrs            4926000 hrs   //Summary Task

      AAA             401 hrs                    401 hrs     // Summary Task

         T1                 350 hrs           350 hrs // Task

         T2                 21 hrs             21 hrs //Task

      BBB             65 hrs                65 hrs      // Summary Task

         T3                 50 hrs                     50 hrs // Task                

         T4                 15 hrs                 15 hrs // Task

     

    against XXX it depicts WORK as 5000000 hrs and ACTUAL WORK as 4926000 hrs instead of 461 and 461

    respectively

     

    could you help me to reslove the issue and let me know if anything else is required

     

    Thanks in Advance

    Santosh

    Monday, May 9, 2011 4:59 PM

Answers

  • Usually, something like that is caused when a resource is assigned to the
    summary task.  Confirm that has not happened in this case.
     
     

    Andrew Lavinsky [MVP] Blog: http://azlav.umtblog.com Twitter: @alavinsky
    Monday, May 9, 2011 5:25 PM