Stop manually scheduled tasks from changing dates when links are added RRS feed

  • Question

  • I have certain milestones within a project plan that are manually scheduled.  If I link those milestones Project automatically recalculates the dates.  Or, if only an end date is populated, Project automatically calculates duration and start dates (which aren't necessarily correct unless of course I add in the correct link-type and offset).  Is there a way to turn off automatic calculation of manually scheduled dates? 

    What I'm trying to achieve is for the gantt chart to simply show the dependency links but to leave the date(s) alone - can this be done?