Project Server locked tasks database field RRS feed

  • Question

  • Where would I find the field mapped to the locked tasks in the Project Server database in order to query tasks that are locked within a projects.?   schema.table.field ? Thanks!
    Wednesday, January 20, 2016 8:06 PM

All replies

  • Hi,

     Task is not getting locked as such in 

      In MSP_EPM_Task there is field called TaskisActive which shows you if task is active or no which I assume you mean by locked and unlocked task. 


    Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS

    Thursday, January 21, 2016 5:31 AM