Project Server 2007 - Assignment details - Update tasks RRS feed

  • Question

  • We are using project server 2007. When we navigate to Tasks->... New tasks->My tasks->Assignment details, we don't have the grid(Work, Actual Work, Overtime as rows, Dates of the week as the columns)  under Task Progress.  We have this grid in test, dev environment.  Hours of work done per period is checked in "Task settings and Display".   Any tips on this?

    Tuesday, September 21, 2010 6:11 PM

Answers

  • Sanjeez --
     
    If you changed the method of tracking progress after the project manager already published the project, the PM needs to publish the project again to refresh the information shown on the Assignment Details page.  If the task is already in progress, however, the task will continue to retain the settings using the old method of tracking progress.  Does that explain what your are seeing?  Let us know and we will try to help.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    • Marked as answer by Sanjeev S K Tuesday, September 21, 2010 7:00 PM
    Tuesday, September 21, 2010 6:50 PM
    Moderator