  • Hello,

    A client I'm working for has requested the ability to see inter-project dependencies across a group of projects (e.g. Program or Portfolio grouping) with a critical path visible throughout, allowing the user to see where a critical path existing across multiple projects.

    Is this possible without having to 'daisy chain' projects via the Subprojects button, or via a custom SSRS report?  This is key functionality and we come across this deficiency on every client engagement.

    Environment:  EPM 2013

    Thanks in advance.

    Nock

    Monday, November 24, 2014 12:37 PM

Answers

  • Hi Nock,

    I'd suggest you to insert your sub-projects into a master project. By default, each inserted project is calculated like summary task:

    Thus calculating the critical path on your master project with this option checked will give you the overall critical path.

    Critical path means depedencies between tasks thus I believe you have to go through using sub-projects and links.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    • Marked as answer by Cherrybar Wednesday, November 26, 2014 4:16 AM
    Monday, November 24, 2014 1:02 PM
    Moderator