Solved: Calendar exceptions dissapearing RRS feed

  • Question

  • Hi,

    I made a resourcepool with all resources of five different disciplines in our company. Assigning a resource is simple, just type in the name in f.e. the task form. But for various resource reports the overview gets a mess. So I decided to split the resourcepool into 5 smaller pools. When I open the initial pool and delete the resources that I don't need in this pool and save it as a new resourcepool, all the calendar exceptions are deleted. Is this a bug or a logical removal? Is there any workaround. Don't feel like retyping all the holidays over and over again.


    Edit: I found the problem. I made a mistake by editing the calendar while in resource view while there was a resource selected. In fact I was editing the resource calendar instead of the general calendar.

    • Edited by Peperbusse Tuesday, December 2, 2014 10:00 AM
    Tuesday, December 2, 2014 7:48 AM

All replies

  • Peperbusse --

    Thanks for letting us know the cause of and solution to your problem.  :)


    Dale A. Howard [MVP]

    Tuesday, December 2, 2014 1:25 PM